Examining the Verrus Data Center Proposal for Salem Oregon

jessewingert
Nov 17
4 min read

On November 9, 2026, the City of Salem held yet another meeting about the Verrus Data Center proposal to build an Artificial Intelligence Data Center in Salem Oregon in Salem’s Mill Creek Corporate Center, at the intersection of Turner Road SE and Deer Park Drive SE.


The Council was to deliberate on the interpretation of "data center facilities" in Salem Revised Code section 400.110(e), and whether to include contemporary AI hyperscaler facilities. The current interpretation dates to 2014, long before the current AI buildout, and technological advances of the past five years"


Mayor-Elect Vanessa Nordyke who currently serves as City Councilor for Ward 7 in Salem opened the meeting celebrating the outcome of the 2026, US mid-term elections.  While her tone from folks on stage was one of a triumph of democracy the sentiment in the room and testimony crowd was a continuation of what Volunteer reporters from Northwest Worker https://www.northwestworker.com/ had previously reported on back in July.


Testimony in Favor:


Those in favor of the Data Center included a marginal contingent of members of the Carpenter’s union testified to their needs for jobs that would be temporarily filled by construction of the data center but did not acknowledge the effects on the community or for the loss of future construction jobs that would be affected because of the data center.   While the trade union members were speaking for their need for jobs they were also parading around with the bosses, paid consultants and one resident who claimed that “data centers are part of our community.”  Their message was that changing interpretation of city codes would cause uncertainty for future developments, and that there are no other jobs nearby.


Testimony in Opposition:


Residents of Salem expressed criticism of city officials.  From one testimonial “You have the power to speak for us and we will be watching.”   


Another told city officials, “Do your jobs and do what we elected you for.” Another said that the Salem Residents “were worth way more than 10 million dollars” and added that that the meeting was “feet from a datacenter; a library.”  


Another testimonial added that “Verus itself has never built a datacenter.” and that “Our community is being used” … “If I sold you a cat and brought you a tiger you would be upset.” … “You cannot provide enough water.” …  “You cannot provide enough electricity.”


Yet another added that Verus are “weasels.  They do not care. I’m sick of coming here and saying this. Stand up for us and say no.”

Another added that “This is not about whether or not Salem wants a data center.” … “Let’s stop wasting time and pay the tradesmen to build the affordable housing we need. Stop wasting our time and stop shopping for new problems and fix the ones we already have.”



The Community Fights Itself


While trade unionists may be fighting for limited-duration employment from the Verrus data center; they have been waiting since July.  At the same time residents of Salem continue to show up opposing the proposal because the data center if constructed would be detrimental to the quality of life for those who live or work in Salem.    Both sides of the community interests into this proposed data center have been waiting for certainty since July.  


It is quite striking that pressing issues for the community surrounding quality of life and jobs in the Salem continue to be centered around this one project proposal that was started in secret, planned in secret and entertained by public officials who would hide their public work from the community they claim to represent.  


For those who want to stay informed the Next Special City Council Meeting where they will be reviewing written commentary submitted by 11/13/2026 will be on November 17, 2026.  


Deliberations - City Council code interpretation of SRC 400.110(e), "data center facilities.



See you there!


Background on Salem Oregon’s Verrus Data Center Proposal

Updated 11/15/2026. 


On July 8, 2026, the city of Salem revealed the city was released from a non-disclosure agreement with SEDCOR a company that chose to partner with Verrus California-based technology company.   Verrus was proposing to build an Artificial Intelligence Data Center in Salem Oregon in Salem’s Mill Creek Corporate Center, at the intersection of Turner Road SE and Deer Park Drive SE.  


Verrus’s public website indicates they are partnering with Emerald AI, Google, NVIDIA, Anthopic and “a broad list” of partners including, all working toward the same goal through their shared AI Energy Management Alliance (AEMA) initiative. 


In response to the secrecy and shady behavior displayed by public and private officials; Salem residents raged against the proposed data center and the city’s Non-Disclosure Agreement (NDA) that kept these plans secret during a public meeting on July 27, 2026.     

Volunteer reporters from Northwest Worker https://www.northwestworker.com/ had previously spoken with members of the Salem Community back in July about the proposed data centers.  What Salem Residents Really Think About the Verrus Data Center (07/27/2026)  


On September 21, 2026, Salem City Council conducted a public hearing and passed a 120-day land use moratorium on data centers.  The city also maintains a Data Center Task Force.  


It wasn’t until October 12 that the city council adopted Resolution 2026-42 to prohibit future data center NDAs. 


The Next Special City Council Meeting

Deliberations - City Council code interpretation of SRC 400.110(e), "data center facilities.

Recent Posts

See All
Background on Salem's Verrus Data Center Proposal

Updated 11/15/2026.  On July 8, 2026, the city of Salem revealed the city was released from a non-disclosure agreement with SEDCOR a company that chose to partner with Verrus California-based technolo

 
 
 